Market Place Sutton works update – April 2017

11 Apr 2017

The renovation of the upper facades are now finally completed – and what a difference it has made.
The shop fronts too are well underway. They will be completed by the end of the April 2017.
There was a bit of an urgency in planting the trees- the planting season ended in the middle of March and the trees had to be planted by then. Four trees have been planted in two locations, making the High Street greener than before.
There will be a pause in the works until the 2nd week of June when work on the paving around the trees, the uplighters, the art work in the alleyways and the new seating will begin. This work will be completed by end of July 2017.
The Council thanks everyone for their patience and tolerance in bearing with the disruption while the works are going on.